Project Name – Engineered Air
Location – Calgary, AB

Project Description

CANA Construction awarded Keystone the Engineered Air project and construction commenced August 22nd, 2016. Engineered Air is a one level parkade addition to their existing building located at 1401 Hastings Crescent SE, Calgary AB. The bulk excavation of this 2,130m2 parkade has been completed and detailed foundation excavation should wrap up early the week of September 12th. The scope of work included; site demo of underground pipes, demo of concrete piles & asphalt, foundation on earthworks and site grading for parking lot and landscape areas.